\chapter{Development Plan}\ChapterLabel{DevelopmentPlan}
|
||||
|
||||
This chapter defines how TikZRefinery will be planned, developed, reviewed, and
|
||||
tested as an individual senior-design project. It converts the mission and
|
||||
constraints in \ChapterRef{TeamDeclaration} into a working process while
|
||||
leaving unbaselined product requirements and implementation feasibility open
|
||||
for review. C++ with Qt is the selected development direction. The plan will be revised when stakeholder feedback, feasibility
|
||||
evidence, or the course schedule changes.
|
||||
|
||||
\section{Introduction}
|
||||
TikZRefinery is intended to become a local desktop application for graphically
|
||||
refining \gls{tikz} diagrams without giving up readable, editable source. The
|
||||
initial development objective is a verifiable end-to-end workflow: accept a
|
||||
supported TikZ document, compile and preview it through a local \gls{latex}
|
||||
toolchain, expose supported objects for graphical manipulation, and reflect an
|
||||
approved edit in source without damaging unsupported content.
|
||||
|
||||
This plan governs the work needed to reach that objective. It addresses
|
||||
responsibility, method, workspace, communication, scheduling, testing, risks,
|
||||
and assumptions. Product behavior is governed separately by
|
||||
\ChapterRef{Requirements}; that chapter will contain the reviewed requirements
|
||||
and mappings needed for later use cases and tests.
|
||||
|
||||
\clearpage
|
||||
\section{Roles and Responsibilities}
|
||||
TikZRefinery is currently an individual project. One person may perform
|
||||
several roles, but the responsibilities remain distinct so that planning,
|
||||
implementation, and review do not become indistinguishable.
|
||||
|
||||
\begin{tabularx}{\linewidth}{@{}L{3.2cm}L{3.3cm}Y@{}}
|
||||
\caption{Development Roles and Responsibilities\label{Table:DevelopmentRoles}}\\
|
||||
\toprule
|
||||
\textbf{Participant or Role} & \textbf{Current Assignment} &
|
||||
\textbf{Responsibilities}\\
|
||||
\midrule
|
||||
Project owner and developer & Vincent Sun & Own scope and priorities; elicit
|
||||
and maintain requirements; design, implement, test, and document the product;
|
||||
retain project records; and approve submitted work.\\
|
||||
Course instructor and project originator & Professor Darian Muresan & Provide
|
||||
the originating project intent, course expectations, early stakeholder
|
||||
feedback, milestone review, and evaluation. Instructor input is evidence and
|
||||
direction for review; implementation remains Vincent's responsibility.\\
|
||||
AI-assisted tooling & OpenAI Codex, under Vincent's review & Assist with
|
||||
research, drafting, coding, consistency checks, builds, and test preparation
|
||||
within the controlled rules in \AppendixRef{AIAgentRequirements}. It does not
|
||||
approve requirements, invent stakeholder evidence, or replace human review.\\
|
||||
Candidate users and reviewers & TikZ and LaTeX users to be identified & Review
|
||||
workflows, terminology, usability, and prototype behavior when access is
|
||||
available. Until then, their presumed needs remain provisional.\\
|
||||
\bottomrule
|
||||
\end{tabularx}
|
||||
|
||||
Vincent is the final decision authority for project execution and academic
|
||||
submissions. The instructor remains the authority for course requirements and
|
||||
grading. If another student, advisor, or external reviewer formally joins the
|
||||
project, this table and the communication plan will be revised before assigning
|
||||
responsibility.
|
||||
|
||||
\subsection{Stakeholder List}
|
||||
Professor Darian Muresan is the currently identified stakeholder beyond the
|
||||
project team. He originated the project idea and has an interest in whether the
|
||||
resulting editor supports the intended graphical TikZ workflow. As course
|
||||
instructor, he also reviews the project's academic milestones. His Qt
|
||||
recommendation is recorded in the method below; specific editing needs still
|
||||
require his review and should not be inferred from that recommendation.
|
||||
|
||||
Vincent is the project owner and developer, as listed above. No additional
|
||||
TikZ or LaTeX users have been confirmed as stakeholders. Their possible needs
|
||||
are represented only by provisional user stories in \ChapterRef{UserStories}
|
||||
until direct feedback is available.
|
||||
|
||||
\section{Method}
|
||||
The project will use a lightweight iterative method rather than claim
|
||||
conformance to a full named process. Weekly work will be selected from reviewed
|
||||
course obligations, product risks, and the current requirements backlog. Early
|
||||
iterations will emphasize feasibility and risk reduction; later iterations
|
||||
will deliver narrow vertical slices that connect source input, compilation,
|
||||
preview, interaction, source update, and verification.
|
||||
|
||||
Each iteration will follow the same working cycle:
|
||||
|
||||
\begin{enumerate}[leftmargin=*]
|
||||
\item Select a small outcome supported by a reviewed requirement or explicit
|
||||
feasibility question.
|
||||
\item Define the acceptance evidence before implementation begins.
|
||||
\item Design and implement the smallest coherent change.
|
||||
\item Run relevant automated and manual tests, record failures, and retain
|
||||
useful evidence.
|
||||
\item Update requirements, risks, decisions, documentation, and the next
|
||||
iteration plan.
|
||||
\end{enumerate}
|
||||
|
||||
Feasibility prototypes answer technical questions but do not by themselves
|
||||
establish completed requirements. Vincent selected C++ with Qt on October 1,
|
||||
2026, following the instructor recommendations as he recalls them. This
|
||||
replaces the earlier PySide6 candidate; no performance comparison was executed
|
||||
to establish that one language is faster for this application. The scaffold
|
||||
uses C++17, Qt 6 Core and Widgets, and CMake. A focused prototype must still
|
||||
open a representative TikZ sample, select and move one supported element,
|
||||
update its source, compile it with a local toolchain, and display the result.
|
||||
Measure responsiveness, implementation complexity, source preservation, and
|
||||
error recovery within the selected implementation. Two complete editor
|
||||
implementations are not planned solely for language comparison.
|
||||
|
||||
\clearpage
|
||||
\subsection{Selected Implementation Design}\label{Section:SelectedImplementationDesign}
|
||||
Vincent agreed the following initial responsibilities and ownership during
|
||||
the October 1--6 design discussion. This adapts the course pattern of recording
|
||||
components and coding conventions to the current development plan; fuller
|
||||
architectural views remain future work. Each primary class has matching
|
||||
\texttt{.h} and \texttt{.cpp} files, grouped under \path{code/src/} by concern.
|
||||
|
||||
\small
|
||||
\begin{tabularx}{\linewidth}{@{}L{4.6cm}L{2.4cm}Y@{}}
|
||||
\caption{Initial Class Responsibilities\label{Table:InitialClassResponsibilities}}\\
|
||||
\toprule
|
||||
\textbf{Class} & \textbf{Folder} & \textbf{Responsibility}\\
|
||||
\midrule\endfirsthead
|
||||
\toprule\textbf{Class} & \textbf{Folder} & \textbf{Responsibility}\\
|
||||
\midrule\endhead
|
||||
\bottomrule\endfoot
|
||||
\texttt{tkrTikzDocument} & \path{model/} & Preserve original source bytes,
|
||||
document revisions, parsed records, and validated minimal edits.\\
|
||||
\texttt{tkrTikzParserExplicit} & \path{parsing/} & Interpret the initial supported
|
||||
syntax and identify editable coordinates and source ranges.\\
|
||||
\texttt{tkrCoordinateMapper} & \path{geometry/} & Convert centimetre coordinates
|
||||
to and from scene positions using documented origin, scale, and axis rules.\\
|
||||
\texttt{tkrEditorController} & \path{controller/} & Coordinate the document,
|
||||
scene, parser, mapper, file loading, and saving.\\
|
||||
\texttt{tkrDiagramScene} & \path{ui/} & Own graphics items and report selection
|
||||
and drag gestures.\\
|
||||
\texttt{tkrMainWindow} & \path{ui/} & Own the application components and provide
|
||||
window controls and unsaved-change handling.\\
|
||||
\end{tabularx}
|
||||
\normalsize
|
||||
|
||||
The current organization also includes \texttt{tkrDiagramView} (viewport fit and
|
||||
paper rendering) and \texttt{tkrEditService} (geometry/replacement preparation).
|
||||
The source-based host-class view is in Section~\ref{Section:CurrentClassDiagram};
|
||||
the planned plugin boundary is in Section~\ref{Section:PluginContract}.
|
||||
|
||||
\noindent\textbf{Ownership.} The window owns the document, controller, and
|
||||
scene. The controller has non-owning references to the document and scene,
|
||||
and owns the parser, mapper and bounded edit service by value. The canvas view
|
||||
is owned through the window's widget hierarchy. The scene owns its graphics items.
|
||||
An accepted final-window close ends the event loop; window destruction then
|
||||
releases its owned components. Save, Discard, or Cancel handles unsaved work.
|
||||
|
||||
\noindent\textbf{Conventions.} Project class names use a lowercase
|
||||
\texttt{tkr} prefix, PascalCase main name, and optional specialization suffix;
|
||||
methods use camelCase.
|
||||
Variables combine type or category prefixes with descriptive meaning; private
|
||||
members add \texttt{m\_}, meaning member. Allow at most three project-defined
|
||||
levels (main/base, child, grandchild), excluding Qt's existing ancestry. The
|
||||
current concrete classes remain \texttt{final}; the module realizes one provider interface
|
||||
for the present prototype. Prefer
|
||||
composition; document non-owning aggregation. Shared records are in
|
||||
\path{model/EditorTypes.h}; details are in \path{code/CODING_GUIDE.md} and
|
||||
Section~\ref{Section:DeveloperRequirements}. The naming and depth clarification
|
||||
was recorded through Vincent's account of instructor feedback on October 15.
|
||||
|
||||
\clearpage
|
||||
\noindent\textbf{Editing and evidence.} Preserve source as bytes with guarded
|
||||
byte ranges. The whole-element workflow previews geometry during a drag, commits
|
||||
source once on release, and restores unchanged source geometry on cancellation.
|
||||
Saving uses \texttt{QSaveFile} with direct-write fallback disabled. The scaffold
|
||||
built successfully on October 20 with Qt 6.12.0 and MinGW 13.1.0; the
|
||||
foundation test passed. Vincent confirmed source display in the running window
|
||||
(Section~\ref{Section:NativeScaffoldCheck}). Rectangle, line and arrow display have
|
||||
bounded checks in Section~\ref{Section:SegmentDisplayCheck}. Whole-element editing
|
||||
and saved-output checks follow in Section~\ref{Section:WholeElementDragCheck};
|
||||
endpoint editing, broader parsing, compiler and PDF display components remain
|
||||
unfinished. This supports \RequirementRef{REQ-A-004}--\RequirementRef{REQ-A-007}
|
||||
and \RequirementRef{REQ-D-001} without marking them complete.
|
||||
|
||||
The MVC allocation in Section~\ref{Section:MVCAllocation} distinguishes the
|
||||
document model, window/scene views, controller, and its parser/mapper services.
|
||||
The responsibility overview in Figure~\ref{Figure:CurrentClasses} links each
|
||||
class to its attributes and operations in
|
||||
Section~\ref{Section:IndividualClassDiagrams} in
|
||||
\ChapterRef{SoftwareArchitecture}. Opening, whole-element dragging, saving, and
|
||||
closing activities remain in \AppendixRef{DesignDocuments}. Existing control flow and future interaction
|
||||
are distinguished in each diagram.
|
||||
|
||||
\clearpage
|
||||
|
||||
\subsection{Review Gates and Change Control}
|
||||
The near-term gates are problem and mission reviewed, development plan
|
||||
reviewed, initial stakeholder stories reviewed, initial requirements and use
|
||||
cases mapped, framework feasibility demonstrated, prototype scope baselined,
|
||||
and end-to-end workflow verified. Passing a gate requires the relevant report
|
||||
content and evidence; a successful demonstration without updated records is
|
||||
not sufficient.
|
||||
|
||||
A material change to mission, scope, supported TikZ syntax, framework,
|
||||
requirement wording, or milestone timing will be assessed for effects on
|
||||
requirements, use cases, architecture, tests, risks, and schedule. Stable
|
||||
identifiers will be preserved, superseded items will be marked Retired rather
|
||||
than deleted, and approved report changes will be entered in Document History.
|
||||
|
||||
\subsection{Initial Work Breakdown}
|
||||
This breakdown groups work by deliverable and review stage. It does not assume
|
||||
that the current candidate requirements or the supported TikZ subset have been
|
||||
approved. Vincent currently owns each work package; tasks can be refined after
|
||||
stakeholder and feasibility review.
|
||||
|
||||
\small
|
||||
\begin{tabularx}{\linewidth}{@{}L{1.6cm}L{3.2cm}Y L{2.0cm}@{}}
|
||||
\caption{Provisional Phase-Level Work Breakdown\label{Table:DevelopmentWorkBreakdown}}\\
|
||||
\toprule
|
||||
\textbf{ID} & \textbf{Work package} & \textbf{Principal output} & \textbf{Depends on}\\
|
||||
\midrule
|
||||
WBS-01 & Needs and scope review & Reviewed stakeholder goals, reference
|
||||
examples when available, candidate requirements, and initial editable boundary
|
||||
& Current proposal\\
|
||||
WBS-02 & Concept and feasibility & Compared approaches, a measured Qt and
|
||||
source-editing prototype, and a recorded language and framework decision &
|
||||
WBS-01\\
|
||||
WBS-03 & Preliminary design & Architecture, source model, interaction flows,
|
||||
compiler boundary, and test design for the selected concept & WBS-02\\
|
||||
WBS-04 & Prototype and alpha evaluation & A working positional-editing path,
|
||||
integrated components, and requirement-linked test evidence & WBS-03\\
|
||||
WBS-05 & Beta refinement and final evaluation & Corrective changes, reviewed
|
||||
evaluation evidence, and the final report and release decision & WBS-04\\
|
||||
\bottomrule
|
||||
\end{tabularx}
|
||||
\normalsize
|
||||
|
||||
\section{Workspace}
|
||||
The private Git repository has separate \path{documents/} and \path{code/}
|
||||
folders. The report source is in \path{documents/latex/}, and the reviewed PDF
|
||||
is in \path{documents/}. Course originals remain as references in
|
||||
\path{documents/template/}. Application source, tests, and examples belong
|
||||
under \path{code/}.
|
||||
|
||||
Development uses Windows, Git, and Visual Studio Code; the report uses the
|
||||
shared TinyTeX installation. The application will invoke a local LaTeX
|
||||
toolchain as an external process. Application development uses the selected
|
||||
C++/Qt direction, with CMake 3.21 or later and a compiler compatible with the
|
||||
installed Qt kit. Qt Core and Widgets are the current dependencies. The
|
||||
October 20 first build used Qt 6.12.0, MinGW 13.1.0, CMake 3.30.5, and Ninja
|
||||
1.12.1. The build and foundation test passed; initial source display was
|
||||
observed. VS Code remains Vincent's preferred editor; Qt Creator is optional.
|
||||
The feasibility gate will assess the workflow described in the Method and
|
||||
Testing Plan.
|
||||
|
||||
The repository root will be the primary folder of a local project in the
|
||||
ChatGPT desktop app so related tasks share files and project instructions.
|
||||
Successive increments may continue in the same chat; a new chat is optional
|
||||
when requested or useful, following Vincent's October 21 preference. The repository's
|
||||
\path{HANDOFF.md} records the current checkpoint and next task; approved
|
||||
requirements and design remain authoritative in this report.
|
||||
\ifSubmissionBuild\else
|
||||
The transition procedure is in Section~\ref{Section:AIChatHandoffs}.
|
||||
\fi
|
||||
|
||||
Git will track authored source and controlled records, while reproducible
|
||||
build artifacts remain ignored. Small edits use Git history for rollback;
|
||||
temporary staging copies are reserved for risky restructuring.
|
||||
|
||||
\clearpage
|
||||
\section{Communication Plan}
|
||||
Because the project currently has one developer, communication emphasizes
|
||||
traceable review rather than internal team meetings.
|
||||
|
||||
\small
|
||||
\begin{tabularx}{\linewidth}{@{}L{3.4cm}L{3.0cm}Y@{}}
|
||||
\caption{Project Communication Plan\label{Table:CommunicationPlan}}\\
|
||||
\toprule
|
||||
\textbf{Communication} & \textbf{Timing} & \textbf{Record or Outcome}\\
|
||||
\midrule
|
||||
Weekly status report & Each assigned reporting week & Completed work, next
|
||||
work, action items, and current issues or risks.\\
|
||||
Instructor discussion and feedback & Classes, milestone reviews, demos, and
|
||||
questions as needed & Clarifications, stakeholder observations, corrections,
|
||||
and decisions reflected in the appropriate controlled chapter.\\
|
||||
Demonstration & At course demo dates & Concise presentation of the most
|
||||
important plan and product evidence, followed by recorded feedback and action
|
||||
items.\\
|
||||
Repository and report review & Before each submission or controlled baseline &
|
||||
Source changes, document version, build result, cross-reference review, and
|
||||
Document History entry.\\
|
||||
AI-assisted work review & Whenever assistance materially affects the project &
|
||||
Prompt-log record, unresolved assumptions, and Vincent's review or correction.\\
|
||||
\bottomrule
|
||||
\end{tabularx}
|
||||
\normalsize
|
||||
|
||||
Instructor feedback will be recorded with its source and date before it is
|
||||
used to revise stories or requirements. Feedback from TikZ or LaTeX users
|
||||
would improve validation if available; absent interviews will not be replaced
|
||||
with invented statements. Initial stories remain open to later correction.
|
||||
|
||||
\clearpage
|
||||
\section{Timeline and Milestones}
|
||||
Work is organized around the milestone sequence shown in the available course
|
||||
slides and the technical dependency from stakeholder intent to verified
|
||||
implementation. The confirmed near-term date is Demo 1 on September 24, 2026.
|
||||
Vincent supplied tentative targets for the later phases: concept development
|
||||
in October--November 2026, preliminary design by November 2026,
|
||||
implementation and alpha evaluation by January 2027, and beta refinement and
|
||||
final evaluation in February--March 2027. These are planning targets, not
|
||||
confirmed course deadlines; they may change with course announcements,
|
||||
instructor feedback, or feasibility results. The chart below is a provisional
|
||||
phase view. A controlled Gantt chart with confirmed dates, task dependencies,
|
||||
critical path, and status will follow when the schedule is established, as
|
||||
required by \ReportRequirementRef{RPT-025}.
|
||||
|
||||
\small
|
||||
\begin{tabularx}{\linewidth}{@{}L{3.0cm}L{2.4cm}YL{2.3cm}@{}}
|
||||
\caption{Development Phases and Milestones\label{Table:DevelopmentMilestones}}\\
|
||||
\toprule
|
||||
\textbf{Phase} & \textbf{Timing} & \textbf{Principal Outcome} &
|
||||
\textbf{Current State}\\
|
||||
\midrule
|
||||
Project definition & Through September 18, 2026 & Team Declaration, mission,
|
||||
drivers, constraints, and initial prototype boundary & Completed and subject
|
||||
to continuing refinement\\
|
||||
Development-plan and inception review & September 22--24, 2026 & Development
|
||||
plan plus initial stakeholder stories, mapped requirements, mapped use cases,
|
||||
glossary and index examples, and supporting citations for Demo 1 & In progress\\
|
||||
Concept development and specification & October--November 2026 (tentative) & Reviewed user
|
||||
needs, requirement baseline, use-case model, concept alternatives, supported
|
||||
TikZ subset, and selected development approach & Planned\\
|
||||
Preliminary design & By November 2026 (tentative) & Architecture, interaction design,
|
||||
source model, compiler boundary, test design, and implementation plan & Planned\\
|
||||
Implementation and alpha evaluation & By January 2027 (tentative) &
|
||||
Working vertical slices, subsystem evidence, integrated alpha scope, and
|
||||
updated cost and schedule data & Planned\\
|
||||
Beta refinement and final evaluation & February--March 2027 (tentative) & Integrated desktop
|
||||
application, performance and usability evidence, controlled release, and final
|
||||
report & Planned\\
|
||||
\bottomrule
|
||||
\end{tabularx}
|
||||
\normalsize
|
||||
|
||||
\clearpage
|
||||
\subsection{Provisional Phase Gantt Chart}
|
||||
The concept and beta phase ranges reflect Vincent's tentative months.
|
||||
November for preliminary design and December--January for
|
||||
implementation and alpha evaluation are illustrative planning windows inferred
|
||||
from the phase sequence and target months; their start dates and any overlap
|
||||
remain unconfirmed. All bars are provisional, and none indicates completed work.
|
||||
|
||||
\begin{figure}[h]
|
||||
\centering
|
||||
\begin{tikzpicture}[x=1.15cm,y=0.9cm,font=\small]
|
||||
\node at (6.5,5.15) {2026};
|
||||
\node at (9.5,5.15) {2027};
|
||||
\foreach \month/\x in {Oct/5,Nov/6,Dec/7,Jan/8,Feb/9,Mar/10} {
|
||||
\node at (\x+0.5,4.65) {\month};
|
||||
}
|
||||
\foreach \x in {5,6,7,8,9,10,11} {
|
||||
\draw[tkrGray!35] (\x,0.55) -- (\x,4.42);
|
||||
}
|
||||
\foreach \y in {0.55,1.48,2.41,3.34,4.42} {
|
||||
\draw[tkrGray!30] (5,\y) -- (11,\y);
|
||||
}
|
||||
\node[anchor=west,text width=4.7cm] at (0,3.87)
|
||||
{Concept development and specification};
|
||||
\node[anchor=west,text width=4.7cm] at (0,2.94)
|
||||
{Preliminary design};
|
||||
\node[anchor=west,text width=4.7cm] at (0,2.01)
|
||||
{Implementation and alpha evaluation};
|
||||
\node[anchor=west,text width=4.7cm] at (0,1.08)
|
||||
{Beta refinement and final evaluation};
|
||||
\fill[tkrBlue!75] (5.08,3.61) rectangle (6.92,4.13);
|
||||
\fill[tkrBlue!30] (6.08,2.68) rectangle (6.92,3.20);
|
||||
\fill[tkrBlue!30] (7.08,1.75) rectangle (8.92,2.27);
|
||||
\fill[tkrBlue!75] (9.08,0.82) rectangle (10.92,1.34);
|
||||
\end{tikzpicture}
|
||||
\caption[Provisional development schedule]{Provisional broad-phase schedule. Dark bars use Vincent's stated
|
||||
ranges; light bars show inferred working windows.\label{Figure:DevelopmentGantt}}
|
||||
\end{figure}
|
||||
|
||||
The immediate critical path is to review stakeholder evidence, define a small
|
||||
supported editing workflow, map initial stories to requirements and use cases,
|
||||
and perform the framework feasibility work. A basic working application must
|
||||
demonstrate that minimum workflow before development expands to broader
|
||||
features.
|
||||
|
||||
\subsection{Possible Future UML Capability}
|
||||
Vincent reports that he and Professor Muresan discussed creating UML diagrams
|
||||
with the editor as a possible later capability. It is outside the minimum
|
||||
positional-editing demonstration. Supported UML notation, generation behavior,
|
||||
and source representation require separate review before becoming requirements.
|
||||
|
||||
\clearpage
|
||||
\section{Testing Plan}
|
||||
Testing will grow with reviewed requirements and implementation. Map each
|
||||
approved product requirement to a use case and repeatable verification method.
|
||||
Keep planned tests, executed tests, and passing evidence distinct.
|
||||
|
||||
\small
|
||||
\begin{tabularx}{\linewidth}{@{}L{3.2cm}Y Y@{}}
|
||||
\caption{Planned Test Levels\label{Table:PlannedTestLevels}}\\
|
||||
\toprule
|
||||
\textbf{Level} & \textbf{Purpose} & \textbf{Representative Evidence}\\
|
||||
\midrule
|
||||
Feasibility tests & Resolve architectural uncertainty before committing to a
|
||||
framework or source-transformation approach & Small executable prototypes,
|
||||
observations, limitations, and decision records\\
|
||||
Unit tests & Verify parsing, model, coordinate, transformation, and
|
||||
source-generation behavior in isolation & Automated inputs, expected outputs,
|
||||
edge cases, and regression results\\
|
||||
Integration tests & Verify interactions among source handling, the external
|
||||
compiler, preview generation, graphical state, and saved output & Controlled
|
||||
sample documents, subprocess results, generated previews, and source diffs\\
|
||||
User-interface tests & Verify principal workflows, feedback, error handling,
|
||||
keyboard or pointer interaction, and recovery & Repeatable procedures, screen
|
||||
evidence when useful, and observed results\\
|
||||
System verification & Demonstrate that the integrated prototype satisfies its
|
||||
approved requirements under the stated environment & Requirement-linked test
|
||||
records and pass/fail evidence\\
|
||||
Stakeholder validation & Determine whether the resulting workflow addresses
|
||||
the actual diagram-refinement problem & Instructor and available user review,
|
||||
demonstration feedback, and resulting actions\\
|
||||
\bottomrule
|
||||
\end{tabularx}
|
||||
\normalsize
|
||||
|
||||
The regression corpus will cover supported examples, malformed input,
|
||||
unsupported constructs, compiler failures, and source preservation during
|
||||
load/save. Maintain detailed cases and results in the testing, traceability,
|
||||
verification, and validation chapters.
|
||||
|
||||
The first geometry checks will independently verify coordinate mapping and
|
||||
move separated boxes into contact (\TestCaseRef{TC-028} and
|
||||
\TestCaseRef{TC-029}). Comparing the editor with a PDF compiled from saved
|
||||
source at a common origin, scale, and fixed extent will guide the conversion
|
||||
design. Start with the explicit-coordinate subset and reference corpus in
|
||||
\ChapterRef{Requirements} and \ChapterRef{Tests}; instructor examples will
|
||||
inform later syntax coverage when available.
|
||||
|
||||
On a documented computer and toolchain, time opening and parsing, graphical
|
||||
movement, source updates, compilation, and preview display separately. Use
|
||||
representative diagrams, including a complex one when available, and record
|
||||
memory use, pauses, failures, and implementation effort. Stakeholder feedback
|
||||
will set quantitative response and preview targets. Investigate measured
|
||||
bottlenecks in the selected C++/Qt implementation and record trade-offs;
|
||||
language choice alone does not establish acceptable performance.
|
||||
|
||||
\clearpage
|
||||
\section{Risks}
|
||||
Likelihood and impact are preliminary qualitative assessments. Vincent owns
|
||||
the current responses and will revise them when feasibility or stakeholder
|
||||
evidence changes the assessment.
|
||||
|
||||
\small
|
||||
\begin{tabularx}{\linewidth}{@{}L{1.4cm}Y L{2.2cm}L{1.4cm}Y@{}}
|
||||
\caption{Initial Development Risk Register\label{Table:DevelopmentRisks}}\\
|
||||
\toprule
|
||||
\textbf{ID} & \textbf{Risk} & \textbf{Likelihood} & \textbf{Impact} &
|
||||
\textbf{Response}\\
|
||||
\midrule
|
||||
\endfirsthead
|
||||
\multicolumn{5}{l}{\small\itshape Initial Development Risk Register (continued)}\\
|
||||
\toprule
|
||||
\textbf{ID} & \textbf{Risk} & \textbf{Likelihood} & \textbf{Impact} &
|
||||
\textbf{Response}\\
|
||||
\midrule
|
||||
\endhead
|
||||
\midrule
|
||||
\multicolumn{5}{r}{\small\itshape Continued on next page}\\
|
||||
\endfoot
|
||||
\bottomrule
|
||||
\endlastfoot
|
||||
RSK-001 & Arbitrary TikZ syntax exceeds the capacity of an individual project.
|
||||
& High & High & Baseline a deliberately limited subset and prioritize one
|
||||
verifiable end-to-end workflow.\\
|
||||
RSK-002 & A graphical edit changes or damages source the application does not
|
||||
fully understand. & High & High & Keep source authoritative, define explicit
|
||||
editing boundaries, preserve unsupported content, show proposed changes, and
|
||||
test round trips against a regression corpus.\\
|
||||
RSK-003 & External LaTeX installations, packages, errors, or execution time
|
||||
produce inconsistent behavior. & Medium & High & Detect tools and packages,
|
||||
run compilation without blocking the interface, capture diagnostics, define a
|
||||
reference environment, and test common failure paths.\\
|
||||
RSK-004 & Untrusted TeX input causes unsafe external-process behavior. & Medium
|
||||
& High & Treat documents as untrusted, use restrictive compilation settings,
|
||||
avoid enabling shell escape by default, and document residual limits.\\
|
||||
RSK-005 & Solo-developer capacity or schedule pressure prevents broad feature
|
||||
coverage. & High & High & Rank work by priority and risk, keep increments
|
||||
small, reserve schedule margin, and defer breadth before weakening the core
|
||||
workflow.\\
|
||||
RSK-006 & The preferred desktop framework or graphics model proves unsuitable.
|
||||
& Medium & Medium & Complete a focused C++/Qt feasibility test before the
|
||||
architecture is baselined, measure the core workflow, and preserve
|
||||
platform-independent requirements.\\
|
||||
RSK-007 & Limited access to additional users leaves usability assumptions
|
||||
weakly validated. & Medium & Medium & Use the instructor as the initial
|
||||
stakeholder, label provisional claims, seek feedback during demos, and add
|
||||
broader user review when feasible.\\
|
||||
RSK-008 & Differences from the previous project's graph/export approach may
|
||||
hide relevant lessons or unsupported assumptions. & Medium & Medium & Its
|
||||
public source and SDK were inspected; compare reusable concepts against our
|
||||
source-preserving contract rather than assuming equivalent behavior.\\
|
||||
\end{tabularx}
|
||||
\normalsize
|
||||
|
||||
\clearpage
|
||||
\section{Assumptions}
|
||||
The following assumptions support planning but are not product requirements.
|
||||
Each will be reviewed as evidence becomes available.
|
||||
|
||||
\begin{tabularx}{\linewidth}{@{}L{1.4cm}Y Y@{}}
|
||||
\caption{Initial Planning Assumptions\label{Table:DevelopmentAssumptions}}\\
|
||||
\toprule
|
||||
\textbf{ID} & \textbf{Assumption} & \textbf{If the Assumption Is Invalid}\\
|
||||
\midrule
|
||||
\endfirsthead
|
||||
\multicolumn{3}{l}{\small\itshape Initial Planning Assumptions (continued)}\\
|
||||
\toprule
|
||||
\textbf{ID} & \textbf{Assumption} & \textbf{If the Assumption Is Invalid}\\
|
||||
\midrule
|
||||
\endhead
|
||||
\midrule
|
||||
\multicolumn{3}{r}{\small\itshape Continued on next page}\\
|
||||
\endfoot
|
||||
\bottomrule
|
||||
\endlastfoot
|
||||
ASM-001 & Explicit-coordinate lines, arrows, and drawn rectangles are adequate
|
||||
for initial feasibility tests. Vincent selected this starting boundary;
|
||||
broader syntax coverage remains a product goal. & Expand the reference corpus
|
||||
using instructor examples and revise the editing approach as needed.\\
|
||||
ASM-002 & Users who need final TikZ output can provide or install a compatible
|
||||
local LaTeX toolchain. & Define clearer setup support or reconsider how
|
||||
compilation and preview are supplied.\\
|
||||
ASM-003 & TikZ source remains the authoritative portable artifact, and the
|
||||
graphical model may represent only supported portions. & Revisit the data model
|
||||
and round-trip objective before implementation continues.\\
|
||||
ASM-004 & Professor Muresan can provide the principal initial stakeholder
|
||||
perspective and early feedback. & Treat the initial stories as incomplete and
|
||||
seek another qualified TikZ or LaTeX user before baselining affected needs.\\
|
||||
ASM-005 & The project will continue with one developer for the current planning
|
||||
period. & Reassign responsibilities and revise communication, schedule, and
|
||||
governance if membership changes.\\
|
||||
ASM-006 & Work can proceed without the previous group's repository. & Continue
|
||||
with independent evidence; if the material arrives, review it for constraints,
|
||||
lessons, and reusable ideas before changing the plan.\\
|
||||
ASM-007 & The Windows development environment can support the selected desktop
|
||||
framework and local compiler integration. & Reassess the framework, supported
|
||||
platform baseline, and schedule using feasibility evidence.\\
|
||||
\end{tabularx}
|
||||
|
||||
These assumptions will be converted into requirements, dependencies, or risks
|
||||
when review shows that they impose a binding obligation or measurable product
|
||||
condition.
|
||||
|
||||
\clearpage
|
||||
\section{Milestone 2 Constraints and Design Iterations}\label{Section:M2Iterations}
|
||||
These constraints come from the project context and reviewed decisions, not
|
||||
from assumed user-study results. Rechecks below are explicitly planned or
|
||||
bounded historical observations.
|
||||
|
||||
\begingroup
|
||||
\small
|
||||
\begin{tabularx}{\linewidth}{@{}L{3.0cm}YY@{}}
|
||||
\caption{Constraints, Alternatives and Consequences\label{Table:M2Constraints}}\\
|
||||
\toprule
|
||||
\textbf{Constraint / driver} & \textbf{Decision and alternative considered} & \textbf{Tradeoff / check}\\
|
||||
\midrule\endfirsthead
|
||||
\toprule
|
||||
\textbf{Constraint / driver} & \textbf{Decision and alternative considered} & \textbf{Tradeoff / check}\\
|
||||
\midrule\endhead\bottomrule\endfoot
|
||||
Solo developer and course deadline & Use a conservative supported subset and focused vertical increments; defer universal syntax and broad refactoring. & Lower coverage in exchange for source safety and reviewable progress; retain corpus regressions and record unsupported forms.\\
|
||||
Editable source must remain authoritative & Choose byte-bound source transactions over regenerating the entire diagram; \RequirementRef{REQ-D-001}, \RequirementRef{REQ-A-008}. & Requires bindings/context and conservative rejection; exact source diffs, shared-definition and history checks detect unintended effects.\\
|
||||
External LaTeX dependencies and variable run time & Preview compilation is separate from live interaction; \RequirementRef{REQ-A-001}, \RequirementRef{REQ-P-001}. & Additional asynchronous state and diagnostics; test slow/failing/missing dependencies and stale preview handling before acceptance.\\
|
||||
Local and offline workflow & Keep core local, subject to stakeholder validation; \RequirementRef{REQ-C-001}, \ValidationRef{VAL-006}. & Local installation/configuration burden; disconnected workflow and dependency diagnostics must be evaluated.\\
|
||||
Overlapping labels and varied source forms & Separate geometry/bindings/capabilities and use explicit selection menus; \RequirementRef{REQ-D-009}, \RequirementRef{REQ-I-008}. & More data contracts and menu interaction; preserve attachments/shared definitions and validate selection with authors.\\
|
||||
Exact undo within finite memory & Start with exact session snapshots; document owns history. & Simple exact restoration costs memory; measure before setting retention/optimization policy. No unreviewed eviction limit is imposed.\\
|
||||
\end{tabularx}
|
||||
\endgroup
|
||||
|
||||
\begingroup
|
||||
\small
|
||||
\begin{tabularx}{\linewidth}{@{}L{2.2cm}YYY@{}}
|
||||
\caption{Documented Feedback-to-Design Iterations\label{Table:M2Iterations}}\\
|
||||
\toprule
|
||||
\textbf{Iteration / finding} & \textbf{Design change} & \textbf{Recheck and evidence} & \textbf{Disposition}\\
|
||||
\midrule\endfirsthead
|
||||
\toprule
|
||||
\textbf{Iteration / finding} & \textbf{Design change} & \textbf{Recheck and evidence} & \textbf{Disposition}\\
|
||||
\midrule\endhead\bottomrule\endfoot
|
||||
ITR-001: October 21 display priority & Vincent reported that lines/arrows did not compile in the editor and prioritized display. Inspection distinguished unsupported editor interpretation from valid original TikZ; the subset was extended. & Eight fixed-extent independent TinyTeX comparisons and six startup fixtures checked display; retained evidence in Section~\ref{Section:SegmentDisplayCheck}. & Completed bounded recheck; broader syntax, native acceptance and integrated compilation remain pending.\\
|
||||
ITR-002: October 27--30 ownership review & Concern about controller responsibility led to document-owned history and controller-owned edit/file services with atomic source/history publication; \RequirementRef{REQ-A-012}--\RequirementRef{REQ-A-014}. & \TestCaseRef{TC-042}, \TestCaseRef{TC-056}, \TestCaseRef{TC-057}; inspect ownership and inject publication/I/O failures. & Design reviewed with Vincent; implementation and rechecks planned.\\
|
||||
ITR-003: October 29 label/selection review & Attached labels and obscured hosts exposed two-point record and hit-selection limits. Separate bindings, attachments and presentation and add point/area candidate menus; \RequirementRef{REQ-D-009}, \RequirementRef{REQ-I-008}--\RequirementRef{REQ-I-010}. & \TestCaseRef{TC-044}, \TestCaseRef{TC-047}, \TestCaseRef{TC-053}, \TestCaseRef{TC-054}, \TestCaseRef{TC-055} and \ValidationRef{VAL-009}, \ValidationRef{VAL-010}; measure observed user problems before adjusting the 6-pixel starting setting. & Owner interaction decisions recorded; code and participant rechecks planned.\\
|
||||
\end{tabularx}
|
||||
\endgroup
|
||||
|
||||
\subsection{Milestone 2 Submission Coverage}
|
||||
Assignment inspected in Vincent's Chrome tab on October 30, 2026:
|
||||
\href{https://sit.instructure.com/courses/188761/assignments/696092}{Milestone 2 -- Project Specification},
|
||||
due October 30 at 11:59 p.m. The required single updated team report is the
|
||||
submission edition; internal AI records remain in the developer edition.
|
||||
|
||||
\begingroup
|
||||
\small
|
||||
\begin{tabularx}{\linewidth}{@{}L{5.0cm}Y@{}}
|
||||
\caption{Milestone 2 Assignment-to-Report Map\label{Table:M2Coverage}}\\
|
||||
\toprule
|
||||
\textbf{Assignment item} & \textbf{Report location / evidence boundary}\\
|
||||
\midrule\endfirsthead
|
||||
\toprule
|
||||
\textbf{Assignment item} & \textbf{Report location / evidence boundary}\\
|
||||
\midrule\endhead\bottomrule\endfoot
|
||||
Bidirectional stories to validation with acceptance criteria & \ChapterRef{UserStories}, \ChapterRef{Validation}; full ten-story map with reciprocal links and planned participant evidence.\\
|
||||
Bidirectional requirements to verification with criteria/method/evidence & \ChapterRef{Requirements}, \ChapterRef{Tests}, \ChapterRef{Verification}; all requirement/check rows are mapped; product acceptance remains pending.\\
|
||||
Use cases, activities, proposed classes and interaction sequences & \ChapterRef{UseCases}, \ChapterRef{SoftwareArchitecture}, \AppendixRef{DesignDocuments}; current and planned diagrams are labelled separately.\\
|
||||
Testing plan with levels, cases, data, outcomes and traceability & Section~\ref{Section:M2TestPlan}, full case register and \ChapterRef{Traceability}; historical results retain dates/limits.\\
|
||||
Dedicated codes/standards applicability and design/check links & \ChapterRef{CodesStandards}; external specifications, adopted guidance and local conventions are distinguished.\\
|
||||
Multiple constraints, tradeoffs and feedback-driven iteration & Tables~\ref{Table:M2Constraints} and \ref{Table:M2Iterations}; one bounded completed recheck plus planned design rechecks.\\
|
||||
\end{tabularx}
|
||||
\endgroup
|
||||
|
||||
\subsection{Course Pattern Adaptation}
|
||||
Adopt stable VER/VAL identifiers and reciprocal maps from the course
|
||||
verification and validation components; adapt their examples into planned local
|
||||
TikZ tasks and measurable oracles, retaining no example Pass claims.
|
||||
Adapt the codes/standards and constraints headings from the course Part II
|
||||
into project-specific content; integrate constraints in this existing plan.
|
||||
Use TikZ class/activity notation and a sequence where atomic interaction order
|
||||
needs explanation. Defer broad 4+1/hardware views without evidence. The temporary
|
||||
open-decisions chapter is explicitly requested by Vincent and will be removed
|
||||
when its decisions have entered the controlled artifacts.
|
||||